Street & Utility Update

roadwork

May 11, 2023

To: Residents within the 2023 Street & Utility Project

Dear Residents,

Here is an update on the Street and Utility work. All timelines listed below are subject to change due to weather conditions or equipment breakdowns. 

Woodland Road & Highwood Drive

Denny Rahn Excavating will be completing the road work this week. The road work will be followed by a WE Energies project around the intersection of Woodland Road and Meadow Lane. This work is expected to begin May 22nd and should take a couple of days. The gas company Project will be followed by concrete work which will be done by DC Burbach. DC Burbach is scheduled to begin May 30th.

Sommerset Avenue & Wirth Street

Dorner Inc. is continuing with the watermain on Wirth Street and will begin Sanitary Sewer work on Sommerset Avenue sometime next week.

Garfield Street

Dorner Inc. is scheduled to begin work on June 5th.

Alley between Franklin Avenue & Evergreen Boulevard

Denny Rahn Excavating is scheduled to begin road work sometime in mid to end of June. This will consist of removing 12 inches of existing asphalt, base and spreading 8 inches of new base course.

All streets continue to be closed to thru traffic. Due to the construction, roadway access and driveway access may be limited during working hours but will be restored at the end of the day.

We ask for your patience during the construction. The entire project will be completed by August 25, 2023. If you have any questions, concerns, or special requests, please let me know. I can be reached at City Hall at (262) 375-7610 or email me at durbanek@ci.cedarburg.wi.us.

CITY OF CEDARBURG

Dylan Urbanek, Assistant City Engineer